SIS Project Tentative Milestones
The following tentative milestones have been established for the SIS Project:
| Expected Date | Milestone |
| November 2007 | Implementation Partner/Consultant Contract Awarded |
| January 2008 | Project Kick-Off |
| September 2008 | Admissions module goes live |
| January 2009 | Financial Aid module goes live |
| March 2009 | Student Records module goes live |
| March 2009 | Student Financials module goes live |
| May 2009 | Student and Faculty Self-Service Centers go live |
| Spring 2009 | Academic Advising module goes live |
| Fall 2009 | All modules up and running, testing completed, assessment and evaluation continues |