| Event |
Date |
| Programming
and Budget |
| Programming Begins |
July 29, 2008 |
| Discuss Draft Program |
January 5, 2009 |
| Program & 10% Concept Design & Budget
for Campus Review Submitted for Approval |
January 19, 2009 |
| Schematic Design |
January-February 2009 |
| Begin EIS |
February 2009 |
| DSF Peer Review |
February 12, 2009 |
| Design Development |
February-March 2009 |
| Work Session, Team Review of 35% Report
|
March 16, 2009 |
| 35% Design Report Complete |
March 30, 2009 |
| Construction Documents |
April-August 2009 |
| BOR, SBC Authority to Construct |
May 2009 |
| Enumeration |
July 2009 |
| EIS Complete |
July 2009 |
| Work Session, Team Review of 100% CD’s
|
August 2009 |
| DSF Review of 100% Documents |
September 2009 |
| A/E Incorporates DSF comments |
October 2009 |
| Issue CD’s for Bidding |
November 2009 |
|
Bidding |
| Start Bidding |
November 2009 |
| Construction Contracts Executed |
December 2009 |
|
Construction |
| Construction (18 months) |
January 2010 – June 2011 |
|
Substantial Completion |
| Commissioning and System Shakedown
|
June 2011 |
| UW- La Crosse Move In and Set Up |
July 2011 |
| Occupancy |
August 2011 |
| Closeout |
December 2011 |