Construction Timeline

Event Date
Programming and Budget
Programming Begins July 29, 2008
Discuss Draft Program January 5, 2009
Program & 10% Concept Design & Budget for Campus Review Submitted for Approval January 19, 2009
Schematic Design January-February 2009
Begin EIS February 2009
DSF Peer Review February 12, 2009
Design Development February-March 2009
Work Session, Team Review of 35% Report March 16, 2009
35% Design Report Complete March 30, 2009
Construction Documents April-August 2009
BOR, SBC Authority to Construct May 2009
Enumeration July 2009
EIS Complete July 2009
Work Session, Team Review of 100% CD’s August 2009
DSF Review of 100% Documents September 2009
A/E Incorporates DSF comments October 2009
Issue CD’s for Bidding November 2009
Bidding
Start Bidding November 2009
Construction Contracts Executed December 2009
Construction
Construction (18 months) January 2010 – June 2011
Substantial Completion
Commissioning and System Shakedown June 2011
UW- La Crosse Move In and Set Up July 2011
Occupancy August 2011
Closeout December 2011