THE GREAT ALPHABET ADVENTURE

Production Team Page

Concept Meeting- Dec 6
Prelim GP/Drawings- Jan 31

Costume Sketches- Jan 31
Budget Meeting- Feb 3
Final GP- Feb 14
Prelim Props & Sound- Feb 14
Final Drawings- Feb 14
Costume Renderings- Feb 14
Build Begins- Feb 24
Prelim Light Plot- March 14
Prop Add Deadline- March 6
Final Sound- March 14
Hang Begins- March 24
Final Light Plot- March 13
Sound Load In- March 24

Focus Begins- March 31
Paper Tech- April 4
Cueing- April 5-6

Tech- April 6-8
Photo Call April 10
Strike- April 12

DOCUMENTS

Weekly Rehearsal Schedule Fittings Sound List
Cast List Character/Scene Breakdown Prop List  
Rehearsal Calendar Director Concept PowerPoint Light Cue List

REPORTS  (click on date to access report)

Sunday Monday Tuesday Wednesday Thursday Friday Saturday
Feb 23 24 25 26 27 28 March 1
2 3 4 5 6 7 8
9 10 11 12 13 14 15
16 17
18 19 20 21 22
23 24 25 26 27 28 29
30 31 April 1 2 3 4 5
6 7 8 9 10 11 12

 

MINUTES

12-6 Concept Meeting
1-31 Production Meeting
2-14 Production Meeting
2-28 Production Meeting
3-7 Production Meeting
3-28 Production Meeting
4-4 Production Meeting