SPRING AWAKENINGProduction Team Page
|
Concept
Meeting-Nov 28 Prelim GP/Drawings- Dec 12 Costume Sketches- Dec 12 Final GP- Jan 16 Prelim Props & Sound- Jan 16 Final Drawings- Jan 16 Costume Renderings- Jan 16 Build Begins- Jan 22 Prelim Light Plot- Feb 6 Hang Begins- Feb 11 Sound Load In- Feb 11 Prop Add Deadline- Feb 13 Final Sound- Feb 13 Final Light Plot- Feb 13 Focus Begins- Feb 20 Paper Tech- Feb 20 Cueing- Feb 23-24 Tech- Feb 27-28 Photocall- March 3 Strike- March 10 |