detroit PRODUCTION TEAM INFORMATION




Prelim GP/Drawings - August 5
Costume Sketches - August 5
Budget Meeting - August 12
Final GP & Drawings - August 19
Prelim Props & Sound - August 19
Costume Renderings - August 30
Build Begins - September 3

Prelim Light Plot - September 18
Hang Begins - September 19

Sound Load In - September 23
Prop Add Deadline - September 25
Final Sound - September 25
Final Light Plot - September 25
Prop View - September 27

Focus Begins - October 7
Paper Tech - October 9

Cueing - October 12-13
Tech - October 14-17
Photocall - October 20
Strike - October 27

DOCUMENTS     

Weekly Rehearsal Schedule    Fittings Prop List  
CAST LIST Character/Scene Breakdown Sound List
Rehearsal Calendar Director Concept PowerPoint Lighting Concept PowerPoint
       
REPORTS (click on date to access report)
Sunday Monday Tuesday Wednesday Thursday Friday Saturday
Sept. 8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23
24 25 26 27 28
29 30 Oct. 1 2 3 4 5
6 7 8 9 10 11 12
13 14 15 16 17 18 19
20 21 22 23 24 25 26
27      

MINUTES

CONCEPT MEETING PRODUCTION MEETINGS
July 5 August 30
September 4
September 11
September 18
September 25
October 2