Parking Ramp Addition

This project phase will design and construct two additional levels with 382 stalls above the 624 stall three level parking ramp constructed in the initial project phase.

At a glance...

Project Budget
The project budget is $7.6 million .

Project Number
The DFD Project Number is 10J2S-02.

Current Status
The project is currently in construction.

Building Size
The building is approximately 130,000 GSF, on two levels.

Location
The location of the addition is above the existing levels of the Parking Ramp.

Timeline
The project is scheduled to begin construction in Spring 2015 and be completed in Fall 2015.