Summer Projects

A page within Planning & Construction

Outside Projects 

On-going Projects 

  • Prairie Spring II Project – Ongoing through January 2029 
    • This summer: 
      • Cowley Hall removed – demo to start late May 
      • Working on electrical disconnection to building currently around footings 
      • May 18-19 – during Steam Shutdown water main work.  
        • Buildings Affected: 
          • Heating Plant
          • East Chiller Plant
          • Murphy Library 
          • Centennial Hall 
          • Wentz Hall 
          • Lowe Center for the Arts 
          • Archaeology Building 

Spring Projects 

  • Stadum Sound and Video Board – Spring 2026 
    • Video board installation 4/13-4/17 
    • Sound system 5/4-5/8 

Summer Projects 

  • Wing IS Project – VCT Replacement 
    • Schedule 5/26-6/5
  • Prairie Spring I roof repair (insurance)   
    • July 2026 
  • Graff Main Hall Roof – Spring/Summer 2026 
    • Mobilizing starting on 04/13 
    • North-west door closed from approximately 4/13 to 6/19 
  • Mitchell Hall Roof – Summer 2026 
    • Schedule 6/8 to 8/14 
  • Murphy Electrical Switch Replacement – Summer 2026 
    • Coordinated with John Jax to pick shut down in early June (TBD) 
    • Power will be off for one day in that timeframe  
  • Murphy Learning Center Renovation – Summer 2026 
    • Start date mid-July 
    • Completion in January 2027 
  • Whitney Steam and Condensate Line – Summer 2026 
    • Mobilizing on 05/18 
    • Schedule  
      • Start 05/18 
      • End 08/21 
      • Pause for WIAA track meet 
      • May impact football practice in early August 

Internal Projects 

On-going Projects 

  • Lenel Doors – Continuing  
    • Completed 
      • Heat Plant 
      • Chiller Plant 
      • North Campus 
    • Current 
      • Archaeology  
      • Stadium 
    • Next 
      • Wing 
      • Cleary 
      • Graff Main 
      • Centennial 
      • Morris 
      • Wimberly 
      • Cartwright 
      • Murphy Library 
      • CFA 

Spring Projects 

  • Mitchell Football and Soccer Locker rooms – Spring/Summer 2026 
    • On schedule to complete before end of Summer 

Summer Projects 

  • Hutchison Hall Lite – Summer 2026 
    • Sleeping Room and Floor Lounge Update 
    • Corridor Update 
    • Schedule 5/18-8/14 
    • Work in Basement and Lobby Summer 2027 
  • Wimberly Auditorium Classroom Chairs – Summer 2026 
    • Approved as part of one-time funds 
    • Chairs are ordered 
    • Existing chairs removed after START  
  • Graff Corridor Furniture – Summer 2026 
    • Approved as part of one-time funds 
    • Working on quotes for order – may divide into two orders 
    • First order planned to be installed by Sept 1 
  • Graff Terrazzo Floors – Summer 2026 
    • Approved as part of one-time funds 
    • Bidding out work for July – one stair at a time 
  • Murphy Library Study Rooms 
    • Approved as part of one-time funds 
    • Working on schedule for work 
  • Potential Restoration of C-11 Parking Lot 
    • Confirming need for construction staging first 
    • Schedule likely July/August (TBD) 
  • Career Services space update  
    • Determining Scope/Schedule/Budget 
  • Records & Registration update 
    • Determining Scope/Schedule/Budget  
  • Classroom Technology Upgrades 
    • Murphy 150, Morris 165 & 175 
      • ~260 hours | Start: May 
    • Centennial - 3 rooms 
      • ~260 hours | Start: July 
    • Computer Lab Replacements 
      • Wing 6 & 7 - ~100 hours | Start: June 
      • Wittich 1100 & 115 - ~80 hours | Start: June 
      • Wimberly 206 - ~80 hours | Start: June 
    • Replace Podium Machines (57 machines) 
      • ~80 hours | Start: June 
    • Reimage All UWL Campus Resources Machines 
      • Murphy Library & remaining computer labs 
      • Podium machines 
      • CASSH department labs 
      • ~160 hours | Start: June 

Standard Summer Work 

  • Summer Classroom Technology Updates 
    • June 
      • Murphy 150 
      • Morris 125 
      • Morris 165 
    • July (possibly – TBD, based on budget) 
      • Centennial 1309 
      • Centennial 1400 
      • Centennial 3310 
      • Centennial 3311 
      • Centennial 3313 
      • Centennial 3314 
      • Centennial 3315 
  • General sidewalk repairs 
    • Locations to be determined  
    • Work in July and early August  

External to Campus (that we’re aware of) 

  • Xcel Energy gas line construction – East Avenue – starts after WIAA 
  • City of La Crosse – reconstruction of Pine Street and N 16th Street  
    • Start right after track meet 
    • Complete by end of August 
    • Will require use of back entrance to South Ramp 
  • City of La Crosse – reconstruction of intersection of Pine Street, Campbell Road and 21st Street 
    • Start right after track meet 
    • Complete by end of August 

Assistance from Planning & Construction