Summer Projects
A page within Planning & Construction
Outside Projects
On-going Projects
- Prairie Spring II Project – Ongoing through January 2029
- This summer:
- Cowley Hall removed – demo to start late May
- Working on electrical disconnection to building currently around footings
- May 18-19 – during Steam Shutdown water main work.
- Buildings Affected:
- Heating Plant
- East Chiller Plant
- Murphy Library
- Centennial Hall
- Wentz Hall
- Lowe Center for the Arts
- Archaeology Building
- Buildings Affected:
- This summer:
Spring Projects
- Stadum Sound and Video Board – Spring 2026
- Video board installation 4/13-4/17
- Sound system 5/4-5/8
Summer Projects
- Wing IS Project – VCT Replacement
- Schedule 5/26-6/5
- Prairie Spring I roof repair (insurance)
- July 2026
- Graff Main Hall Roof – Spring/Summer 2026
- Mobilizing starting on 04/13
- North-west door closed from approximately 4/13 to 6/19
- Mitchell Hall Roof – Summer 2026
- Schedule 6/8 to 8/14
- Murphy Electrical Switch Replacement – Summer 2026
- Coordinated with John Jax to pick shut down in early June (TBD)
- Power will be off for one day in that timeframe
- Murphy Learning Center Renovation – Summer 2026
- Start date mid-July
- Completion in January 2027
- Whitney Steam and Condensate Line – Summer 2026
- Mobilizing on 05/18
- Schedule
- Start 05/18
- End 08/21
- Pause for WIAA track meet
- May impact football practice in early August
Internal Projects
On-going Projects
- Lenel Doors – Continuing
- Completed
- Heat Plant
- Chiller Plant
- North Campus
- Current
- Archaeology
- Stadium
- Next
- Wing
- Cleary
- Graff Main
- Centennial
- Morris
- Wimberly
- Cartwright
- Murphy Library
- CFA
- Completed
Spring Projects
- Mitchell Football and Soccer Locker rooms – Spring/Summer 2026
- On schedule to complete before end of Summer
Summer Projects
- Hutchison Hall Lite – Summer 2026
- Sleeping Room and Floor Lounge Update
- Corridor Update
- Schedule 5/18-8/14
- Work in Basement and Lobby Summer 2027
- Wimberly Auditorium Classroom Chairs – Summer 2026
- Approved as part of one-time funds
- Chairs are ordered
- Existing chairs removed after START
- Graff Corridor Furniture – Summer 2026
- Approved as part of one-time funds
- Working on quotes for order – may divide into two orders
- First order planned to be installed by Sept 1
- Graff Terrazzo Floors – Summer 2026
- Approved as part of one-time funds
- Bidding out work for July – one stair at a time
- Murphy Library Study Rooms
- Approved as part of one-time funds
- Working on schedule for work
- Potential Restoration of C-11 Parking Lot
- Confirming need for construction staging first
- Schedule likely July/August (TBD)
- Career Services space update
- Determining Scope/Schedule/Budget
- Records & Registration update
- Determining Scope/Schedule/Budget
- Classroom Technology Upgrades
- Murphy 150, Morris 165 & 175
- ~260 hours | Start: May
- Centennial - 3 rooms
- ~260 hours | Start: July
- Computer Lab Replacements
- Wing 6 & 7 - ~100 hours | Start: June
- Wittich 1100 & 115 - ~80 hours | Start: June
- Wimberly 206 - ~80 hours | Start: June
- Replace Podium Machines (57 machines)
- ~80 hours | Start: June
- Reimage All UWL Campus Resources Machines
- Murphy Library & remaining computer labs
- Podium machines
- CASSH department labs
- ~160 hours | Start: June
- Murphy 150, Morris 165 & 175
Standard Summer Work
- Summer Classroom Technology Updates
- June
- Murphy 150
- Morris 125
- Morris 165
- July (possibly – TBD, based on budget)
- Centennial 1309
- Centennial 1400
- Centennial 3310
- Centennial 3311
- Centennial 3313
- Centennial 3314
- Centennial 3315
- June
- General sidewalk repairs
- Locations to be determined
- Work in July and early August
External to Campus (that we’re aware of)
- Xcel Energy gas line construction – East Avenue – starts after WIAA
- City of La Crosse – reconstruction of Pine Street and N 16th Street
- Start right after track meet
- Complete by end of August
- Will require use of back entrance to South Ramp
- City of La Crosse – reconstruction of intersection of Pine Street, Campbell Road and 21st Street
- Start right after track meet
- Complete by end of August